Israel's 2015 natural gas framework was a government plan to regulate development of the major offshore reserves, ownership and sale of gas, exports, and competition among suppliers. Its central dispute concerned whether the government could promise regulatory stability for ten years while future governments and the Knesset retained their legal powers.
What the plan addressed
The framework set conditions for field development and required changes in the holdings of companies with interests in multiple fields. It also covered domestic supply, export limits, and the government's use of an exemption under the then-applicable restrictive trade practices law. The plan aimed to give investors a clearer regulatory path for expensive offshore projects while setting rules for market structure and domestic availability.
What the court decided
In March 2016, the High Court of Justice ruled that the framework's stability clause could not stand. The clause bound the government for ten years on regulatory matters including taxation, competition rules, and export caps. The majority held that this unlawfully restricted the discretion of the government and future decision-makers. The court's judgment did not hold that the whole framework was invalid on every ground; it gave the state time to address the stability problem, and justices differed on whether the entire plan would otherwise need to be annulled.
The government adopted a revised framework in May 2016 with a narrower stability arrangement. The legal and political argument centered on balancing predictable investment conditions with the authority of future governments and lawmakers to change policy. The decision is therefore best understood as a ruling against the original stability clause, not a blanket court rejection of natural gas development.
The Supreme Court decision is available as Movement for Quality Government v. Prime Minister. The Finance Ministry retains meeting protocols and materials from the framework's preparation. The government's 2016 decisions document subsequent regulatory action. For the resource base, see the Tamar and Leviathan guide.