The IAEA’s authority in Iran comes from distinct legal arrangements. Iran’s NPT safeguards agreement, in force since 1974, covers nuclear material in peaceful nuclear activities and requires Iran to cooperate with verification. An Additional Protocol provides broader information and access that help the Agency assess whether declarations are complete. The 2015 JCPOA added temporary monitoring measures beyond those safeguards. The Agency has repeatedly distinguished routine accounting of declared material from questions about undeclared past activity and the completeness of Iran’s declarations.
Three layers of verification
Under its comprehensive safeguards agreement, Iran must report nuclear material and permit Agency verification at safeguarded facilities. Iran signed an Additional Protocol in 2003, applied it voluntarily from December 2003 to February 2006, then began provisional application under the JCPOA in January 2016. In February 2021, Iran stopped implementing the JCPOA’s nuclear-related monitoring commitments, including provisional application of the Additional Protocol. The IAEA’s June 2025 report explains the safeguards agreement’s legal basis and the different measures. Its GOV/2025/25 report is explicit that the Additional Protocol broadens verification beyond the basic agreement.
What remained unresolved in 2025
In June 2025, the Agency reported that Iran had not provided technically credible answers about safeguards questions linked to undeclared nuclear material or activities at locations including Lavisan-Shian, Varamin and Turquzabad. It concluded that the available information indicated an undeclared structured nuclear program carried out until the early 2000s, involving undeclared nuclear material at some locations. It said it had no credible indications of an ongoing undeclared structured program of that type. The same report called Iran’s production and accumulation of uranium enriched to 60% a serious concern, while emphasizing that safeguarded enrichment is not prohibited by itself. These findings should be read together; the report does not say that the Agency had established an active weapons program. See the Agency’s overall assessment and safeguards findings.
Inspections after the June 2025 attacks
The IAEA reported that attacks on nuclear installations from 13 to 24 June 2025 caused it to stop in-field verification and withdraw inspectors for safety. Iran passed a law suspending cooperation on 2 July. In its September report, the Agency said it had not received nuclear-material accountancy reports or updated design information since 13 June and had no access to safeguarded facilities other than Bushehr. It continued to assess facilities using commercial satellite imagery and open information. That describes a verification gap: satellite observation cannot replace inspection, sampling or material accountancy. The September 2025 report documents the change. For the legal framework and deal-era monitoring, see what the JCPOA required.